Mr. Kumar is getting his house renovated. 1/5 th of the work has been completed in 2 months. How much time will it take for the entire work to be completed?

Respuesta :

liam2747
liam2747 liam2747
  • 02-05-2021

Answer:

10 months

Step-by-step explanation:

If it takes 2 months to do 1/5th, it will take 4 months to do 2/5, 6 months to do 3/5, 8 months to do 4/5, and 10 months to do 5/5 or in other words the whole thing.

Answer Link

Otras preguntas

What is the root word of educator and it's meaning
Non-steroid hormones are made of amino acids, so they are proteins. True or false
Which spanish city is known for the fact that people of three different religions peacefully lived there together? (1 point) Avila Madrid Segovia Toledo
What were three things that contributed to American culture?
What was the significance of the Code of Hammurabi? The laws were developed from an ancient Sumerian code of laws. The laws were displayed throughout the empire
equation for the points (3,8) (2,6) on slope
The feeling of fervent devotion toward one’s nation above all others is known as?
Which of the following sentences contains an italicized word that's used as a predicate adjective? A. Jerry looks at the map. B. Jerry looks ill today. C. Jerry
John's age is 4 more than 3 time Mike's age. If their sum is 20, how old are Mike and John?
what are the small communities