The top-down method of estimating project time and costs that is useful for projects requiring the same task, group of tasks, or product repeated several times, especially if it is labor intensive, is the ______________.
a) function point
b) ratio
c) apportion
d) consensus
e) learning curves

Respuesta :

parisannthornton parisannthornton
  • 04-08-2021
The answer is e) learning curves
Answer Link

Otras preguntas

how to curl your hair with a curling iron
what is the meaning of good friday
What is the rule of (0,-2)(1,1)(2,4)(3,7)(4,10)
the founder of the annual medical science awards that are often called “america’s nobels” is also considered the founder of what field?
as electrons are passed through the system of electron carriers associated with photosystem ii, they lose energy. what happens to this energy?
which of the following is an arrhenius acid? a brønsted–lowry acid? a lewis acid? it is possible for an acid to be of more than one type.
hi can someone translate these to english? only if you know french so please no translator because that wont help me at all. Où va cette famille pendant les va
upper respiratory infection
how to increase metabolism
who were the first europeans to master fireworks