8 students take 18 hours to construct a raft.
If the raft needs to be completed 12 hours earlier, calculate how many more students are needed.

Respuesta :

devishri1977
devishri1977 devishri1977
  • 04-08-2021

Answer:

16

Step-by-step explanation:

Students                      8       x

Time taken (hours)     18     18 - 12 = 6

If number of students increases, the work will completed in less hours.

So inverse proportion

[tex]x =\frac{18*8}{6}=3*8 = 24[/tex]

Additional students required = 24 - 8 = 16

Answer Link

Otras preguntas

How do I solve problem 10?
If you need to extract a 50 ml aqueous solution with 50 ml of dichloromethane, what is the minimum size of a separatory funnel you will have to use to safely ca
Name the three nations that were considered the major colonizers of the new world.
what does homeostasis mean.
How did the pre-Socratic philosophers lay the foundations for science?
Madison wants to make cookies for his little sisters birthday party she is cutting a roll of cookie goes into pieces that are 1/2 inch thick if the role is 13
When you are giving a presentation, which of these elements will help you to explain the content better
what was the key issue at the constitutional convention?
words that rhyme with ready
which fraction is the smallest 11/15 3/5 2/3 5/6