If you walk 5.0 m horizontally forward at a constant velocity carrying a 10 N object, the amount of work you do is

Respuesta :

iciclepiano18
iciclepiano18 iciclepiano18
  • 04-03-2022

Answer:

50 J

Explanation:

The equation for Work is:

[tex]Work=Force*Distance[/tex]

We can substitute the given values into the equation:

[tex]Work=10N*5.0m\\Work=50J[/tex]

Answer Link

Otras preguntas

What are two different ways to describe and label the layers of the Earth?
.is a pot holder a conductor or a insulator
A 1 digit number and a 3 digit number have a sum of 205.  The same two number have a difference of 195, a product of 1,000 and a quotient of 40.  What are the t
How is the numeral 35.012 written in words and why
A passenger on a boat moving at 1.70 m/s on a still lake walks up a flight of stairs at a speed of 0.60 m/s , as shown in the figure . The stairs are angled at
in an expression(8/9) squared (-81)+3/5dividedby-9/10
How does transpiration play a  role in the water cycle ?
is it possible for a distance versus-time graph to be a vertical line?
is it possible for a distance versus-time graph to be a vertical line?
When was William Shakespeare born